ADDITIONAL WORK PERFORMANCE:
(a) All crossings over the highway shall be constructed in accordance with
"Specifications for Overhead Crossings of Light and Power Transmission Lines and
Telegraph Lines over each other and over Highway Rights of Way in South
Carolina," as approved by the Public Service Commission of South Carolina and
effective as of date of this permit.
(b) All tunneling, boring, or jacking shall be done in such a way as not to
disturb the highway surfacing.
(c) No pavement shall be cut unless
specifically authorized herein.
(d) No excavation shall be nearer than three feet to the edge of pavement unless
specifically authorized herein.
(e) Underground facilities will be located at minimum depths as defined in the
"Utility Accommodations Manual" for the transmittant, generally as follows: 4
feet minimum for hazardous or dangerous transmittant, 3 feet minimum for other
lines. The Department may approve shallower depths if adequate protection is
provided. Such approval must be obtained in writing.
(f) Service and other small diameter pipes shall be jacked, driven, or otherwise
forced underneath the pavements on any surfaced road without disturbing the
pavement. The section under the highway pavement and within a distance of three
(3) feet on either side shall be continuous without joints.
(g) Any vegetation removed due to the permitted work, should be replaced in accordance with the Department's "Standard Specifications For Highway Construction" and the "Supplemental Technical Specifications" for seeding (SC-M-810-3), and at the expense of the Permittee.